Immediately after screeding concrete to
the finished level, lay the Crack Inducer (with or without
capping) with its bottom edge along the proposed joint line.
Roll the Crack Inducer so that it is
vertical and wriggle it into the wet concrete until the
top edge is flush with the finished level of the slab.
Trowel along the Crack Inducer to fill
any voids created during placement. Complete finishing operations
and application of any applied finishes.
If capping was used in the installation,
remove the tear off strip by carefully pulling it back along
the length of the joint